Tuesday, May 5, 2009

Nothing

Finally the additional leech drain sand has been removed. Hopefully the sparkie will be back by the end of the week.( 2nd fix) He wants to meet with us to check that downlights will be where we want them We are hoping that gives us a chance to remind him of the power point buried in plaster in the kids study/activity room. We also hope to have a conversation about placement of the batten lights for the kitchen and office to make sure their positions suit us.

Asked about handover and was told that although it as still possible it "might" be at the end of May/beginning of June that we should tell the cork flooring people mid June in case of delays. sigh.. A bit disappointing as it doesn't seem there is that much to do.
* 2nd fix of electrical including oven to be fitted. starting this week( fingers crossed)
*Painting to be completed.- stain and varnish front door and 3 jarrah caps.
-paint laundry door and small garage door with final coat.
-Paint, currently missing, manhole cover
- Final coat of power box and fit door.
- Other final coats????doors?
*Garage sectional panelift door to be installed
*Insulation in ceiling
*Minor plaster and mortar patching Maybe at PCI
*External Slider in dining to be fixed. Hopefully b4 PCI
* House to be cleaned
* Yard cleanup and rock removal, trench to be covered over.
* Porta loo and waste bin to be removed.
* Window in main bedroom doesn't seem to seal closed properly. PCI ?

No comments: